CPI require a Principal Contractor to deliver the Design and Build of the Medicines Manufacturing Innovation Centre as described within the ITT and supporting documentation included with this procurement;
The design and build contract will be on the basis of a two stage appointment.
The first stage will be in accordance with a Pre-Construction Services Agreement and the second stage in accordance with a NEC4 Engineering and Construction Contract Option A, Priced Contract with Activity Schedule for which the Works Information and Site Information are described in the Tender Appendices.
Appointment to the second stage will follow successful completion of the first stage.
For the avoidance of doubt, delivery of the process equipment operating in the cleanrooms is not part of this scope. However, the detailed design of the cleanrooms must consider the requirements of this process equipment.
NB. The award of this contract is NOT conditional on the approval of grant funding which has already been awarded.
CPI require a Principal Contractor to deliver the Design and Build of the Medicines Manufacturing Innovation Centre as described within the ITT and supporting documentation included with this procurement;
The design and build contract will be on the basis of a two stage appointment.
The first stage will be in accordance with a Pre-Construction Services Agreement and the second stage in accordance with a NEC4 Engineering and Construction Contract Option A, Priced Contract with Activity Schedule for which the Works Information and Site Information are described in the Tender Appendices.
Appointment to the second stage will follow successful completion of the first stage.
For the avoidance of doubt, delivery of the process equipment operating in the cleanrooms is not part of this scope. However, the detailed design of the cleanrooms must consider the requirements of this process equipment.
NB. The award of this contract is NOT conditional on the approval of grant funding which has already been awarded.
CPI awarded tender 1396 - Design and Build of the Medicines Manufacturing Innovation Centre (MMIC) to Interserve Construction Limited under 2019/S 245-602089, during the build programme, costs have exponentially increased due to pandemic cost increases, programme delays due to AMIDS development and therefore this modification notice is increasing the awarded value to the upper limit of modification allowable against this contract.