The rehabilitation project funded by the EIB focuses on the Dnipro regional power system which involves up to 9 substations. In general, the rehabilitation project includes the replacement of high voltage circuit breakers, measurement transformers, disconnectors, control and protection devices, auxiliary power systems including batteries, AC/DC distribution panels, the installation of server/computer hardware, routers and software for data acquisition and local communication and control.
Version of 2020-11-13
Substation construction work
The rehabilitation project funded by the EIB focuses on the Dnipro regional power system which involves up to 9 substations. In general, the rehabilitation project includes the replacement of high voltage circuit breakers, measurement transformers, disconnectors, control and protection devices, auxiliary power systems including batteries, AC/DC distribution panels, the installation of server/computer hardware, routers and software for data acquisition and local communication and control.
Version of 2020-10-12
Substation construction work
The rehabilitation project funded by the EIB focuses on the Dnipro regional power system which involves up to 9 substations. In general, the rehabilitation project includes the replacement of high voltage circuit breakers, measurement transformers, disconnectors, control and protection devices, auxiliary power systems including batteries, AC/DC distribution panels, the installation of server/computer hardware, routers and software for data acquisition and local communication and control.
Rehabilitation of substations includes the replacement of high voltage circuit breakers, measurement transformers, disconnectors, control and protection devices, auxiliary power systems including batteries, AC/DC distribution panels, the installation of server/computer hardware, routers and software for data acquisition and local communication and control.