As part of the enhancements to the existing Hayle Marine Renewables Business Park (HMRBP) in West Cornwall, and under Phase 2 of its development, Cornwall Council is seeking to appoint a suitably experienced and qualified Construction company to act as Principal Contractor and undertake works for the following:
The construction of 6 new BREEAM Excellent workspace units (circa 1 475 m
The works are anticipated to start on site during June 2021 and will need to be completed during June 2022 to meet European Regional Development Fund (ERDF) requirements.
The relevant tender documentation and all formal communications or queries regarding this opportunity must only be accessed or made via the supplyingthesouthwest.org.uk portal, under Project Reference DN509481
Version of 2021-01-19
Construction work
As part of the enhancements to the existing Hayle Marine Renewables Business Park (HMRBP) in West Cornwall, and under Phase 2 of its development, Cornwall Council is seeking to appoint a suitably experienced and qualified Construction company to act as Principal Contractor and undertake works for the following:
The construction of 6 new BREEAM Excellent workspace units (circa 1 475 m
The works are anticipated to start on site during April 2021 and will need to be completed during May 2022 to meet European Regional Development Fund (ERDF) requirements.
The relevant tender documentation and all formal communications or queries regarding this opportunity must only be accessed or made via the supplyingthesouthwest.org.uk portal, under Project Reference DN509481.
Following the success of the Phase 1 development, Cornwall Council are seeking a suitably and demonstrably experienced principal contractor to undertake the works to construct the second phase of Hayle Marine Renewables Business Park, at North Quay, Hayle, Cornwall, TR27 4DD. The form of construction contract will be an NEC 3 Engineering and Construction Contract 2013 Edition (Option A) with secondary options and z clauses as included with the procurement documents, and appointment will be on a traditional basis with contractor design packages. Phase 2 will involve expanding the site west towards the existing Wave Hub site, and North on to land currently owned by Western Power. Land acquisition is well progressed and the majority of agreed conditions have been addressed; completion is expected prior to contract award and the contractor will be notified of any update to this position by way of a clarification should it become available during the tender period.
The project is part-funded by the European Regional Development Fund (ERDF) and the contractor will be required to comply with all relevant EU Regulations and specifically the Branding and Publicity Guidelines required of an ERDF funded project. The Ministry of Housing, Communities and Local Government (MHCLG) as Managing Authority for the European Regional Development Fund (ERDF) programme has completed the technical appraisal of the full application and approved in principle the award of ERDF grant. The pre-offer ERDF conditions have been cleared and at the time of writing the Council is awaiting receipt of the funding agreement. Any update to this position will be shared with all tenderers by way of a tender clarification. At present, a steel fence divides the site, and there is a level variation that will need to be overcome by the project.
On the land owned by Cornwall Council, the project will deliver 5No. BREEAM Excellent light industrial units (Building 1) with office and workspace at ground floor,office use mezzanines and solar PVs, totalling circa 1 119 m
On the land owned by Western Power, the project will deliver 1no. BREEAM Excellent light industrial unit (Building 2) with office and workspace at ground floor, office use mezzanine and solar PVs, totalling circa 369 m
The contractor will be responsible for obtaining each of the BREEAM credits targeted during RIBA Stages 5 and 6 and will also be responsible for discharging each of the outstanding planning conditions listed within the works information. The Council anticipates the contract Award to take place during April 2021, with completion and occupation of the new facilities during May 2022.