This notice supplements previously published notice from Elektrownia Wiatrowa Baltica – 2 SP. Z o.o. 2022/S 171-485697 (Works). This notice is published on a voluntary basis in order to increase transparency and knowledge about Ørsted Entities' purchases in EU tender procedures.
This notice relates to the Contracting Entity’s project for the development, construction and operation of an offshore wind project in the Baltic Sea with a total potential capacity of up to 1.5 GW and consist of 107 WTG and 4 OSS locations where Ørsted Wind Power A/S is representing the Contracting Entity in the entire tender procedure (‘Entity represented by Ørsted Wind Power A/S’), specifically to the tender for the relocation of boulders at the WTG and OSS jack up locations. The Baltica 02 project is located some 50 km offshore in the Polish part of the Baltic Sea.
Ørsted Wind Power A/S will use the UNCE qualification system for procurement and expects to launch the tender via said qualification system on week 43-45 (23. October – 10. November 2023) using product code 4.1.18 Demolition & Clearance Work.
This notice supplements previously published notice from Elektrownia Wiatrowa Baltica – 2 SP. Z o.o. 2022/S 171-485697 (Works). This notice is published on a voluntary basis in order to increase transparency and knowledge about Ørsted Entities' purchases in EU tender procedures.
This notice relates to the Contracting Entity’s project for the development, construction and operation of an offshore wind project in the Baltic Sea with a total potential capacity of up to 1.5 GW and consist of 107 WTG and 4 OSS locations where Ørsted Wind Power A/S is representing the Contracting Entity in the entire tender procedure (‘Entity represented by Ørsted Wind Power A/S’), specifically to the tender for the relocation of boulders at the WTG and OSS jack up locations. The Baltica 02 project is located some 50 km offshore in the Polish part of the Baltic Sea.
Ørsted Wind Power A/S will use the UNCE qualification system for procurement and expects to launch the tender via said qualification system on week 43-45 (23. October – 10. November 2023) using product code 4.1.18 Demolition & Clearance Work.
Version of 2023-05-08
Construction work
This notice supplements previously published notice from Elektrownia Wiatrowa Baltica – 2 SP. Z o.o. - 2022/S 171-485697 (Works). This notice is published on a voluntary basis in order to increase transparency and knowledge about Ørsted Entity purchases in EU tender procedures.
This notice relates to the contracting entity's project for the development, construction and operation of offshore wind project in the Baltic Sea with a total potential capacity of up to 1.5 GW where Ørsted Wind Power A/S is representing the Contracting Entity in the entire tender procedure (‘Entity represented by Ørsted Wind Power A/S’), specifically to the tender for Transport and Installation of Foundations and Offshore Substations.
Ørsted Wind Power A/S will use the Achilles Utilities NCE qualification system for procurement and expects to commence the tender in May/June 2023, using Commodity Codes 2.8.6 Transportation Services and 4.4.23 Wind Farm Construction.
This notice supplements previously published notice from Elektrownia Wiatrowa Baltica – 2 SP. Z o.o. - 2022/S 171-485697 (Works). This notice is published on a voluntary basis in order to increase transparency and knowledge about Ørsted Entity purchases in EU tender procedures.
This notice relates to the contracting entity's project for the development, construction and operation of offshore wind project in the Baltic Sea with a total potential capacity of up to 1.5 GW where Ørsted Wind Power A/S is representing the Contracting Entity in the entire tender procedure (‘Entity represented by Ørsted Wind Power A/S’), specifically to the tender for Transport and Installation of Foundations and Offshore Substations.
Ørsted Wind Power A/S will use the Achilles Utilities NCE qualification system for procurement and expects to commence the tender in May/June 2023, using Commodity Codes 2.8.6 Transportation Services and 4.4.23 Wind Farm Construction.
Version of 2023-05-08
Construction work
This notice supplements previously published notice from Elektrownia Wiatrowa Baltica – 2 SP. Z o.o. and Elektrownia Wiatrowa Baltica – 3 SP. Z o.o. 2022/S 171-485697 (Works). This notice is published on a voluntary basis in order to increase transparency and knowledge about Ørsted Entities' purchases in EU tender procedures.
This notice relates to the contracting entity project for the development, construction and operation of offshore wind project in the Baltic Sea with a total potential capacity of up to 1.5 GW where Ørsted Wind Power A/S is representing the Contracting Entity in the entire tender procedure (‘Entity represented by Ørsted Wind Power A/S’), specifically to the tender for Landfall Horizontal Directional Drilling (HDD) and associated works.
Ørsted Wind Power A/S will use the UNCE qualification system for procurement and expects to launch the tender via said qualification system as early as of week 27 of 2023 using product code "4.3.10 Trenchless Pipe Laying".
Only companies registered in the specified product code at the time when the Prequalification Notice is issued can apply for the prequalification. If you intend to participate as a Consortium, please note that the Consortium or all participating entities should be registered in the abovementioned product codes.
The Scope of Work for the tender under the UNCE qualification system will be for Landfall Horizontal Directional Drill (HDD) and associated works for Baltica 2 project.
The scope consists of all activities necessary to complete the construction of 4 x HDD for Baltica 2. Comprising of a single HDPE duct for each HDD. It is envisaged that the HDPE Ducts will be 1150m each of 900mm HDPE SDR11.
The HDPE Ducts will facilitate the subsequent installation of export cables between the Offshore Wind Farm and the onshore grid network. The cable installation scope is undertaken under a separate contract and is not part of this tender.
The landfall site is located within the Village of Lubiatowo, on the northern coast of the Pomerania Voivodeship, approximately 20km East of Łeba and 50km North-West of Gdynia. Contract Award will expectedly be Q1 2024. Pre-Commencement Activities will take place at the Site, which will be available for selected Contractor from Q1 2025. The expected installation year is 2025.
This notice supplements previously published notice from Elektrownia Wiatrowa Baltica – 2 SP. Z o.o. and Elektrownia Wiatrowa Baltica – 3 SP. Z o.o. 2022/S 171-485697 (Works). This notice is published on a voluntary basis in order to increase transparency and knowledge about Ørsted Entities' purchases in EU tender procedures.
This notice relates to the contracting entity project for the development, construction and operation of offshore wind project in the Baltic Sea with a total potential capacity of up to 1.5 GW where Ørsted Wind Power A/S is representing the Contracting Entity in the entire tender procedure (‘Entity represented by Ørsted Wind Power A/S’), specifically to the tender for Landfall Horizontal Directional Drilling (HDD) and associated works.
Ørsted Wind Power A/S will use the UNCE qualification system for procurement and expects to launch the tender via said qualification system as early as of week 27 of 2023 using product code "4.3.10 Trenchless Pipe Laying".
Only companies registered in the specified product code at the time when the Prequalification Notice is issued can apply for the prequalification. If you intend to participate as a Consortium, please note that the Consortium or all participating entities should be registered in the abovementioned product codes.
The Scope of Work for the tender under the UNCE qualification system will be for Landfall Horizontal Directional Drill (HDD) and associated works for Baltica 2 project.
The scope consists of all activities necessary to complete the construction of 4 x HDD for Baltica 2. Comprising of a single HDPE duct for each HDD. It is envisaged that the HDPE Ducts will be 1150m each of 900mm HDPE SDR11.
The HDPE Ducts will facilitate the subsequent installation of export cables between the Offshore Wind Farm and the onshore grid network. The cable installation scope is undertaken under a separate contract and is not part of this tender.
The landfall site is located within the Village of Lubiatowo, on the northern coast of the Pomerania Voivodeship, approximately 20km East of Łeba and 50km North-West of Gdynia. Contract Award will expectedly be Q1 2024. Pre-Commencement Activities will take place at the Site, which will be available for selected Contractor from Q1 2025. The expected installation year is 2025.
Version of 2023-01-31
Prefabricated units and components
This notice supplements previously published notice from Elektrownia Wiatrowa Baltica – 2 SP. Z o.o. and Elektrownia Wiatrowa Baltica – 3 SP. Z o.o. 2022/S 171-485697 (Works). This notice is published on a voluntary basis in order to increase transparency and knowledge about Ørsted Entities' purchases in EU tender procedures.This notice relates to the contracting entities projects for the development, construction and operation of two offshore wind projects in the Baltic Sea with a total potential capacity of up to 2.5 GW where Ørsted Wind Power A/S is representing the Contracting Entities in the entire tender procedure (‘Entities represented by Ørsted Wind Power A/S’), specifically to the tender for the Manufacture and Supply of Secondary Structures.Ørsted Wind Power A/S will use the UNCE qualification system for procurement and expects to launch the tender via said qualification system in March 2023 using product code 4.4.23.
This notice supplements previously published notice from Elektrownia Wiatrowa Baltica – 2 SP. Z o.o. and Elektrownia Wiatrowa Baltica – 3 SP. Z o.o. 2022/S 171-485697 (Works). This notice is published on a voluntary basis in order to increase transparency and knowledge about Ørsted Entities' purchases in EU tender procedures.This notice relates to the contracting entities projects for the development, construction and operation of two offshore wind projects in the Baltic Sea with a total potential capacity of up to 2.5 GW where Ørsted Wind Power A/S is representing the Contracting Entities in the entire tender procedure (‘Entities represented by Ørsted Wind Power A/S’), specifically to the tender for the Manufacture and Supply of Secondary Structures.Ørsted Wind Power A/S will use the UNCE qualification system for procurement and expects to launch the tender via said qualification system in March 2023 using product code 4.4.23.