North Ayrshire Council requires a new build primary school including a nursery which will be built on the site of the old Glengarnock Academy in Kilbirnie. This will be a replacement for the current Moorpark Primary School.

The contract duration will be 65 weeks construction period and expected contract start date is August 2020.

Extended TitleNAC/5013 New Build Primary School, Kilbirnie
Extended Description

The construction of a predominately single storey new build primary school and nursery (approx. total area 3 000 m2), together with extensive external works.

The works include groundworks, glulam timber frame, cross laminated timber structure, structural timber walls, brickwork, roof and wall cladding, joiner work, wall finishes, floor finishes, suspended ceilings, fixed furniture, decoration, siphonic roof drainage, plumbing, mechanical and electrical installations together with associated site works, underground drainage and external services.

Deadline Date2020-04-13
Publication Date2020-03-12
CountryUnited Kingdom
Procurement StatusActive
TypeOpen procedure
Contract TypeWorks
Award CriteriaThe most economic tender
Value8650000
OrganisationNorth Ayrshire Council
AddressCunninghame House, Friars Croft
TownIrvine
Postal CodeKA12 8EE
Phone+44 1294310000
Class Code45214200
Class DescriptionConstruction work for school buildings
SourceOffice for Official Publications of the European Communities - Tenders electronic daily (Ted)

Version of 2020-01-17

Construction work for school buildings

North Ayrshire Council are looking to notify the market of this future contract opportunity.

It is anticipated that this will be advertised early March 2020 as an open tender on the Public Contracts Scotland National Advertising Portal and all appropriate compliant channels. The procurement exercise will be carried out via the PCS-Tender E-tendering system.

North Ayrshire Council would welcome notes of interest at this stage. Please note, you will still be able to submit a tender for this procurement exercise without having to note your interest at this stage.

We would request that only parties genuinely interested in pricing these works express an interest. If you have the relevant experience and capacity to carry out this project within the required timeline please email Al Foster at procurement@north-ayrshire.gov.uk to note your interest by 12.2.2020.

Extended TitleNAC/5013 New Build Primary School, Kilbirnie
Extended Description

Background

North Ayrshire Council requires a new build Primary School including a Nursery which will be built on the site of the old Glengarnock Academy in Kilbirnie. This will be a replacement for the current Moorpark Primary School.

The contract duration will be 65 weeks construction period and expected contract start date is August 2020.

Description of requirement

The construction of a predominately single storey new build primary school and nursery (approx. total area 3 000 m2), together with extensive external works.

The works include groundworks, glulam timber frame, cross laminated timber structure, structural timber walls, brickwork, roof and wall cladding, joiner work, wall finishes, floor finishes, suspended ceilings, fixed furniture, decoration, siphonic roof drainage, plumbing, mechanical and electrical installations together with associated site works, underground drainage and external services.

Publication Date2020-01-17
CountryUnited Kingdom
Procurement StatusFuture
TypeNot applicable
Contract TypeWorks
Award CriteriaNot applicable
Value8650000
OrganisationNorth Ayrshire Council
AddressCunninghame House, Friars Croft
TownIrvine
Postal CodeKA12 8EE
Phone+44 1294310000
Class Code45214200
Class DescriptionConstruction work for school buildings
SourceOffice for Official Publications of the European Communities - Tenders electronic daily (Ted)

Related Procurements

The Council is keen to engage with organisations involved in the development and delivery of affordable and supported housing, to provide high-level feedback on the initial sites and approaches being...
View more
Deadline: Oct 27, 2020
This framework will cover the supply and installation of communal doors, entrance doors and associated products, including cyclical maintenance for multi occupancy residential buildings (low/medium/high rise) educational establishments, local government...
View more
Deadline: Oct 27, 2020
This framework will cover the supply and installation of communal doors, entrance doors and associated products, including cyclical maintenance for multi occupancy residential buildings (low/medium/high rise) educational establishments, local government...
View more